Construction project

DIVISION 1
1. Identify all general condition items needed to complete this project. This includes, but not
limited to: salaries for supervisory personnel, temporary facilities, utility bills …etc. Read the
plans, review the lectures, and use your common sense and knowledge to find related items
from RS Means.
DIVISION 3
1. This project includes concrete slab and footing per drawings, identified as S1A. The other
alternative shown in drawing S1 (footings and foundation walls) should not be used.
2. Footings (including turndown) and slab concrete to be 3500 psi and 4000 psi, respectively.
3. Consider following items, separately, for footings (including turndown) and slab-on-grade:
Concrete forming, Concrete reinforcement, and Concrete placement (including curing and
finishing, where applicable)

DETAILED ASSIGNMENT