MGT 3410 Managenent

  • Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) complete date is desired. The condominium manager identified the following renovation activities and their estimated times:
  • Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:
Activity Immediate Predecessor Time
A 3
B 1
C 2
D A, B, C 4
E C, D 5
F A 3
G D, F 6
H E 4
  • Draw a project network.
  • What are the critical activities?
  • Will the project be completed by September 1?
Activity Immediate Predecessor Time (weeks)
Optimistic Most Probable Pessimistic
A 1.5 2.0 2.5
B A 2.0 2.5 6.0
C 1.0 2.0 3.0
D C 1.5 2.0 2.5
E B, D 0.5 1.0 1.5
F E 1.0 2.0 3.0
G B, D 3.0 3.5 7.0
H G 3.0 4.0 5.0
I F, H 1.5 2.0 2.5
  • Draw a project network.
  • What are the critical activities and what is the expected project completion time?
  • If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?